Here are the Project Time Management Processes
- Activity definition: Identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.
- Activity sequencing: Identifying and documenting the relationships between project activities.
- Activity resource estimating: Estimating how many resources a project team should use to perform project activities.
- Activity duration estimating: Estimating the number of work periods that are needed to complete individual activities.
- Schedule development: Analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule.
- Schedule control: Controlling and managing changes to the project schedule.
Another piece I've leaned was the Three Types of Dependencies
- Mandatory dependencies: Inherent in the nature of the work being performed on a project; sometimes referred to as hard logic.
- Discretionary dependencies: Defined by the project team; sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.
- External dependencies: Involve relationships between project and non-project activities
Sample Activity-on-Arrow (AOA) Network Diagram