I've finally am able to remember what the nine bodies of knowledge that are identified by the (PMI) project management institute. And they are:
- IntegrationScope
- Time
- Human Resources
- Cost
- Risk
- Communications
- Procurement
- Planning
I know now how to complete a "Three Point Estimate" for a project. I'll show you what I mean: "Say that the project optimistically can finish in 3 days, most likely will finish in 7 days but, could take as long as 17 days." Below is the equation you would use.
3+ (4 * 7) +17 = 48 = 8 Days
6 6
Here's just a few other bits that I have learned over the past few classes.
-A Stakeholder analysis is a project management tool that can be used to help manage relationships with different people involved in a project.
-The main reason why firm incest in information technology projects is actually because they want to support explicit business objectives.
-The project charter is the document formally recognizes the existence of a project.
-The WBS is the main output of the scope definition process and is also an outcome-oriented analysis of the work involved in a project that defines the total scope of the project.
-You must make sure someone has completed the first draft from Finish - Start in order to start editing a technical report.